New Museum & Cultural Centre Project

New Museum & Cultural Centre Project


Project Start Date: Spring 2019

Expected Completion Date: May 2021
 

Project Overview

Construction of a new single-story museum and cultural centre approximately 8,400 total gross sq. ft. on the site of the old museum with renewed pedestrian access across the historic site to the Twenty Mile Creek. Full details are available in the project background.
 

 

Project Milestones & Progress

  • Fencing around the site reconfigured completed

    Completion date: August 20, 2019

  • Site preparations and clearing completed

    Completion date: August 22, 2019

  • Construction trailer onsite completed

    Completion date: August 22, 2019

  • Water & sewer connections completed

    Completion date: September 10, 2019

  • Site excavation for the footings and foundation completed

    Completion date: September 30, 2019

  • Footings and foundation completed

    Completion date: October 2019

  • Underground hydro connections by NPEI completed

    Completion date: November 2019

  • Main floor core slab installed completed

    Completion date: November 2019

  • Framing of exterior walls completed

    Completion date: January 10, 2020

  • Exterior walls, structural steel roof & windows completed

    Completion date: February 2020

  • Masonry work on main floor & elevator shaft completed

    Completion date: February 2020

  • Installation of roof truss & deck completed

    Completion date: February 2020

  • Exterior wall sheathing completed

    Completion date: February 2020

  • Roof membrane completed

    Completion date: March 2020

  • Exterior spray foam insulation completed

    Completion date: May 2020

  • Interior wall framing completed

    Completion date: August 2020

  • Mechanical rough in completed

    Completion date: September 2020

  • Electrical rough in completed

    Completion date: September 2020

  • Drywall completed

    Completion date: September 2020

  • Window installation completed

    Completion date: September 2020

  • Painting completed

    Completion date: October 2020

  • Wood ceiling completed

    Completion date: October 2020

  • Exterior cladding completed

    Completion date: December 2020

  • Main level floor completed

    Completion date: December 2020

  • Exterior doors completed

    Completion date: December 2020

  • Niagara Peninsula Energy Inc. connection completed

    Completion date: December 2020

  • Commissioning of the HVAC system completed

    Completion date: December 2020

  • Commissioning of the lighting system completed

    Completion date: December 2020

  • Interior doors and hardware completed

    Completion date: January 2021

  • Mechanical finishes completed

    Completion date: January 2021

  • Electrical finishes completed

    Completion date: January 2021

  • Millwork completed

    Completion date: February 2021

  • Bathroom work completed

    Completion date: March 2021

  • Carpeting and baseboard completed

    Completion date: January 2021

  • Painting completed

    Completion date: January 2021

  • Elevator delivered and installation begins

    Target completion date: April 2021

  • Elevator installation

    Target completion date: April 2021

  • TSSA approval

    Target completion date: April 2021

  • Building inspections and occupancy permit issued

    Target completion date: April 2021

  • Substantial completion

    Target completion date: April 2021

  • Deficiencies to be completed

    Target completion date: April 2021

  • High density storage system install

    Target completion date: May 2021

  • Installation of opening exhibit

     Target completion date: May 2021

Please note that the project schedule is subject to change due to COVID-19 restrictions.


Project Team:

  • Shannon McKay, B.A., PMP, Director, Community Services
  • Sean Jackson, PMP, C.Tech., Project Manager
  • David Warden, Manager of Public & Open Spaces
  • Matt Bruder, MCIP, RPP, Associate Director of Planning and Development
  • Walter Neubauer, CET, Manager – Technical Services
  • Sarah Ane - Associate Director, Recreation and Culture
  • Jessica Wilson – Cultural Development Coordinator
  • Jasmine Proteau – Acting Cultural Development Coordinator
  • Olivia Rozema – Cultural Events Program Administrator
  • Stephanie Bellisimo – Collections Curator
  • Beth Labrie – Cultural Interpreter
  • Consultants:
    • Paul Sapounzi, Lead Partner, +VG The Ventin Group Architects
    • Travis Forrest, Associate Partner, Project Manager, +VG The Ventin Group Architect
       

Contact Information: 

Sean Jackson, Project Manager, email or call 905-563-2799 ext. 258

 

 

Date modified: