New Museum & Cultural Centre Project

New Museum & Cultural Centre Project


Project Start Date: Spring 2019

Expected Completion Date: Summer 2020
 

Project Overview

Construction of a new single-story museum and cultural centre approximately 8,400 total gross sq. ft. on the site of the old museum with renewed pedestrian access across the historic site to the Twenty Mile Creek. Full details are available in the project background.
 

    Project Progress (October-December 2019)

    • Grant was received from David S. Howes Fund Grant for $25,000 (towards the Museum shelving system)
    • Lower floor concrete slab is completed
    • Structual steel is completed
    • Main floor core slab has been installed
    • Stairs to lower level has been installed
    • NPEI has installed underground conduit on Main street from the transformer by the Inn on the Twenty to the Museum site


    Progress Photo Gallery

     

    Project Milestones & Progress

    • Fencing around the site reconfigured completed

      Completion date: August 20, 2019

    • Site preparations and clearing completed

      Completion date: August 22, 2019

    • Construction trailer onsite completed

      Completion date: August 22, 2019

    • Water & sewer connections completed

      Completion date: September 10, 2019

    • Site excavation for the footings and foundation completed

      Completion date: September 30, 2019

    • Footings and foundation completed

      Completion date: October 2019

    • Underground hydro connections by NPEI completed

      Completion date: November 2019

    • Main floor core slab installed completed

      Completion date: November 2019

    • Framing of exterior walls completed

      Completion date: January 10, 2020

    • Exterior walls, structural steel roof & windows

      Target completion: March 2020

    • Masonry work on main floor & elevator shaft

      Target completion date: February 2020

    • Installation of roof truss & deck to begin

      Target completion date: February 2020

    • Exterior insulation & cladding to be installed

      Target completion date: March 2020

    • Window installation

      Target completion date: Mid April 2020



    Project Team:

    • Shannon McKay, B.A., PMP, Director, Community Services
    • Sean Jackson, PMP, C.Tech., Project Manager
    • David Warden, Manager of Facilities
    • Matt Bruder, MCIP, RPP, Associate Director of Planning and Development
    • Walter Neubaur, CET, Manager – Technical Services
    • Sylvia Beben, Events & Programs Facilitator
    • Lisa Mercier, Museum Curator
    • Consultants:
      • Paul Sapounzi, Lead Partner, +VG The Ventin Group Architects
      • Travis Forrest, Associate Partner, Project Manager, +VG The Ventin Group Architect
         

    Contact Information: 

    Sean Jackson, Project Manager, email or call 905-563-2799 ext. 258

     

     

    Date modified: